# Thin-Pod rev 0.1: Prototype Bring-Up and Ground-Return Limitation
**Project:** Thin-Pod
**Release documented:** rev 0.1
**Prepared by:** Neil Thomson / Pealie
**Document status:** Prototype evidence and ground-return limitation record
**Document date:** 26 May 2026
## 1. Purpose
This document records the relationship between:
1. the first physically manufactured Thin-Pod prototype used for electrical bring-up;
2. the ground-return issue found at the Qorvo DWM3001-CDK interface during that work; and
3. the evidence boundary for the Thin-Pod rev 0.1 open-hardware release and OSHWA certification record.
The document prevents two opposite errors: concealing a real bring-up issue, or presenting an unimplemented copper correction as completed release evidence.
## 2. Prototype objective
The first Thin-Pod PCB prototype was created to establish the electrical viability of a compact vibration-sensing carrier board. Its immediate aims were:
- to validate the protected power-entry and regulated supply path;
- to verify the switched accelerometer supply;
- to examine the analogue output and filtered measurement node from an ADXL1005-based sensing section;
- to confirm that an attached Qorvo DWM3001-CDK could form part of the intended pod-side interface; and
- to gather evidence for a release-quality open-hardware design and record its limitations.
The broader Gateway, wireless communications implementation, DSP and TinyML path sat outside this first PCB bring-up.
## 3. Prototype hardware under test
The prototype included the following relevant design blocks:
| Design block | Function |
|---|---|
| RAW_IN power input | External power entry to the carrier board |
| Fuse provision and 1N5817 diode | Basic input protection and reverse-polarity protection |
| Pololu S7V8F3 module | Local regulated 3.3 V supply |
| ZVP2106A PFET circuit | Switched supply control for the sensor section |
| ADXL1005-based sensing interface | Analogue vibration signal production |
| Analogue filtering / ADC node | Conditioned sensor signal for observation and downstream sampling |
| TP1–TP7 | Bring-up and measurement access points |
| Qorvo DWM3001-CDK interface | Commercial CDK connection for intended pod-side processing/radio development |
## 4. Bring-up discovery: CDK ground return
### 4.1 Observed behaviour
During initial testing of the assembled prototype, the intended CDK power/interface arrangement failed to provide the expected usable ground-return connection through the assumed path. The attached CDK showed expected behaviour only after its negative/reference connection was bonded to a confirmed CDK ground point.
### 4.2 Temporary prototype correction
A short temporary ground connection was added between the relevant CDK return point and a known functional CDK ground reference. This was a bring-up workaround applied to the physical prototype in order to continue testing the sensor-node electrical path.
The temporary connection served a diagnostic purpose:
- it established a common electrical reference for the attached CDK/interface arrangement;
- it allowed the board to proceed through powered testing; and
- it revealed the relevant ground-return path for any future corrected design.
### 4.3 Engineering classification
The finding is treated as a **design-interface limitation in the pre-release carrier-board implementation**: the interface design relied on a ground-return assumption that proved inadequate in physical bring-up. The outcome is recorded explicitly as part of the rev 0.1 evidence boundary.
A copper-level correction remains a future design option rather than completed rev 0.1 release evidence.
## 5. Prototype measurement evidence after temporary correction
With the temporary ground-return connection in place, prototype testing established proof of life for the essential analogue sensor-node chain.
| Measurement / observation | Prototype result | Interpretation |
|---|---|---|
| Power-up after CDK ground-reference correction | Successful | Prototype could proceed with powered validation once the interface return was established |
| Switched accelerometer supply rail, `/ACC_3V3_SW` | Approximately 3.35 V | Sensor supply path was active and close to the intended 3.3 V rail |
| Filtered sensor output / `SENSOR_SIGNAL_FILTERED` / ADC-node measurement | Approximately 1.76 V at rest | Mid-rail biased analogue output consistent with a 3.3 V-powered analogue accelerometer signal path |
| Gentle tap / mechanical excitation response | Clearly observable on the oscilloscope | The sensor/analogue observation path responded to physical vibration |
These measurements demonstrate the functional promise of the power and analogue signal portions of the prototype. Wireless sampling, packet transport, Gateway processing and analytic fault detection require separate evidence.
## 6. Rev 0.1 ground-return evidence boundary
The rev 0.1 documentation records the CDK ground-return issue as a prototype finding and known limitation. The temporary jumper allowed bring-up to continue, but it should not be described as a completed copper correction in the released source or fabrication outputs.
The relevant exposed CDK ground pins identified for any future corrected implementation are:
```text
J1_2 GND ─┐
J10_6 GND_1 ─┤
J10_9 GND_2 ─┤
J10_14 GND_3 ─┼── GND
J10_20 GND_4 ─┤
J10_25 GND_5 ─┘
```
The project-local, Thin-Pod-authored CDK mating-interface footprint remains part of the release source:
```text
ThinPod_DWM3001CDK_Mating_Interface_revA_KiCad10.kicad_mod
```
A future correction would require an updated schematic/PCB, regenerated Gerbers and a dated verification record. If fabrication cost or project direction makes that unattractive, the limitation can remain documented rather than implemented.
## 7. Versioning position
The ground-return finding belongs in the **Thin-Pod rev 0.1** record because it was discovered during the first physical bring-up and directly affects interpretation of the prototype evidence.
The copper-level correction should be treated as a future revision only if it is implemented in source, regenerated into fabrication outputs and verified on hardware. This document preserves the prototype history without implying that builders of rev 0.1 receive a verified copper-level correction.
## 8. Verification boundary
The evidence must be read precisely.
| Claim | Status |
|---|---|
| A pre-release prototype PCB was fabricated and assembled | Verified |
| The prototype required a temporary CDK ground-reference correction during bring-up | Verified and recorded |
| The power and analogue signal path displayed successful proof-of-life behaviour after the prototype correction | Verified and recorded |
| The released rev 0.1 KiCad source includes a copper-level ground-return correction | Deferred; future revision only if implemented |
| The released rev 0.1 Gerbers include a copper-level ground-return correction | Deferred; future regenerated outputs only if implemented |
| A newly manufactured PCB from corrected Gerbers has been tested without the temporary wire | Deferred; future measurement only if a corrected board is manufactured |
## 9. Evidence to include in the repository
The following files or images should be placed in the public release repository where available:
| Evidence item | Suggested location |
|---|---|
| Photographs of the first manufactured prototype PCB | `images/prototype-bring-up/` |
| Photograph of the temporary ground-return correction | `images/prototype-bring-up/` |
| Oscilloscope image showing tap response | `images/prototype-bring-up/` or `images/test-evidence/` |
| Recorded voltage measurement images or log extract | `images/test-evidence/` |
| Screenshot of current CDK interface mapping | `images/released-design/` |
| Screenshot of current PCB / Gerber interface area | `images/gerber-inspection/` |
| Gerber archive from the current release design | `hardware/fabrication/` |
## 10. Future physical confirmation test if a correction is implemented
If a future revision implements the CDK ground-return correction in copper, a board fabricated from the regenerated corrected Gerbers should be tested using the following focused procedure:
1. Visually inspect the new board and confirm correct CDK connector orientation.
2. Use continuity mode, with power removed, to confirm carrier `GND` continuity to `J1_2`, `J10_6`, `J10_9`, `J10_14`, `J10_20` and `J10_25`.
3. Confirm no short exists between the intended supply rail and `GND`.
4. Install the CDK without the prototype ground jumper.
5. Apply current-limited power under the correct supply conditions.
6. Confirm expected CDK power behaviour and stable sensor supply.
7. Repeat the analogue rest-bias and mechanical-excitation observation.
8. Update `docs/design-verification.md` with measured results and dated evidence.
## 11. Conclusion
The first Thin-Pod prototype achieved its central purpose: it revealed both a viable analogue vibration-sensing path and a correctable interface defect. The OSHWA-facing rev 0.1 record now treats the CDK ground-return issue as a known evidence boundary. The temporary jumper belongs to the documented history of disciplined prototype bring-up; any future copper correction belongs to a later implemented and verified design update.